Construction

Project timeline as of January 2024

Upcoming Construction Plans

  • Complete new walls and ring beam at the West Holding Tank.
  • Complete installation of the Pre-engineered Metal Building for the Biosolids Building & Cake Loadout
  • Repair East Holding Tank upper walls and construct new roof.
  • Refurbish DAF 1 and 2 into the new sidestream treatment system.
  • Complete High Mast Lights.

Work Completed

February 2024

  • Procured FRP doors and frames, additional ductile iron piping, stainless steel piping, FRP & aluminum ductwork and other mechanical items and additional R.E. Pedrotti instrumentation.
  • Installed high mast lighting
  • Formed and poured the transformer pad and set the transformers
  • Continued installing duct bank at the north side of the Digesters
  • Continued installing piping and ductwork at various areas of the Biosolids Building.
  • Continued installing the Pre-Engineered Metal Building framed openings and insulated wall panels.
  • Continued stucco work at the Digester Building and Transfer Area.
  • Continued electrical rough-in for cable tray and conduit at several areas of the Biosolids Building.
  • Continued working on the WHT wall rebuild.
  • Continued working on the Sidestream equipment and piping installation in Reactor No. 2.
  • Continued painting CMU walls and piping at the Biosolids Building.

January 2024

  • Procured concrete paving dowel baskets, overhead doors, FRP doors and hardware, acid scrubber tank, hydraulic elevator, additional valves, ductile iron piping, stainless steel piping, HVAC equipment and other mechanical items, VFDs, additional R.E. Pedrotti instrumentation, transformers, and other electrical items.
  • Continued work on the burnished block upper wainscot and brick at the Biosolids Building exterior walls.
  • Continued installing piping and ductwork at various areas of the Biosolids Building.
  • Continued installing the Pre-Engineered Metal Building (PEMB) secondary steel and framed openings.
  • Started installing the PEMB insulated metal wall panels
  • Continued work installing the lower roof metal deck.
  • Installed the bridge crane.
  • Started stucco work at the Digester Building basement.
  • Continued electrical rough-in for cable tray and conduit at several areas of the Biosolids Building.
  • Continued working on the WHT wall rebuild.
  • Continued working on Sidestream equipment installation in Reactor No. 2.

December 2023

  • Procured the casings for the high mast lighting, additional valves, ductile iron piping, stainless steel piping, HVAC equipment and other mechanical items, the new elevator equipment, World Waterworks Sidestream control panels and VFDs and additional R.E. Pedrotti instrumentation.
  • Completed installing the interior CMU wall at the Screen Room.
  • Continued installing the burnished block upper wainscot and brick at the Biosolids Building exterior walls.
  • Continued installing piping and ductwork at the Boiler Room, Screen Room, Truck Bay, Centrifuge Feed Pump Room and THP area.
  • Continued installing the Pre-Engineered Metal Building (PEMB) secondary steel and started trimming out for the PEMB openings.
  • Completed installing the bridge crane rails.
  • Poured the 2” thick cap over the precast hollow core roof at the Upper Floor Electrical Room.
  • Finished installing the metal stairs at the south end of the Biosolids Building.
  • Continued installing anchors for cable tray and conduit at several areas of the Biosolids Building.
  • Started working on the WHT wall rebuild.
  • Began installing the Sidestream equipment in Reactor No. 2.

November 2023

  • Procured additional valves, ductile iron piping, HVAC equipment and other mechanical items, Velodyne polymer feed equipment, World Waterworks Sidestream equipment and additional R.E. Pedrotti instrumentation.
  • DunPar completed removing all shoring for the Upper Deck pours.
  • Continued installing the burnished block upper wainscot and brick at the north Biosolids Building wall.
  • Installed the balance of the Velodyne polymer skids at the Polymer area,.
  • Continued installing piping and ductwork at the Boiler Room, Screen Room, Truck Bay and THP area.
  • Installed the Pre-Engineered Metal Building (PEMB) primary steel and started on the secondary steel and installed the bridge crane beams.
  • Installed the precast hollow core roof over the Upper Floor Electrical Room.
  • Started metal stair installation at the south end of the Biosolids Building.
  • Continued installing anchors for cable tray and conduit at several areas of the Biosolids Building.

October 2023

  • Procured the polymer manhole, additional valves, ductile iron piping, and other mechanical items, centrifuges, Velodyne polymer feed equipment, Vogelsang rotary lobe pumps, additional R.E. Pedrotti instrumentation, boilers, deaerator skids and light fixtures.
  • Installed odor control yard piping.
  • Completed additional vinyl ester coating on equipment pads.
  • Completed installing rebar and poured the north section of the Upper Deck.
  • Continued installing the burnished block upper wainscot.
  • Began installing the CMU walls at the Upper level electrical room.
  • Installed most of the Velodyne polymer skids at the Polymer area.
  • Installed the boilers and DA Tank skids.
  • Continued installing piping and ductwork at the Boiler Room.
  • Installed the rotary lobe screen pumps at the Sludge Pump Room.
  • Completed pouring the Acid Scrubber Pad.
  • Installed lighting and conduit at the Pre-THP Cake room.
  • Poured the operating floor of the Cake Loadout structure.

September 2023

  • Procured additional valves, ductile iron piping, and other mechanical items, JMS sludge silo materials, Velodyne polymer feed equipment, primary pad mounted switches, World Water Works Sidestream equipment, Vogelsang rotary lobe pumps and additional R.E. Pedrotti instrumentation.
  • Formed and poured the Primary Switch pad and set the new switches.
  • Started up the relocated existing sludge transfer pump.
  • Continued installing rebar and setting forms for the Upper Deck and completed the middle slab pour.
  • Continued installing brick veneer around the Biosolids Building, installed CMU at the south
  • Biosolids Building stairwell, began installing the burnished block upper wainscot.
  • Installed additional sludge screening piping at the Polymer area.
  • Installed piping and ductwork at the Boiler Room.
  • Installed the THP Cooling Tower and fan.
  • Continued working on screened sludge piping at the Sludge Pump Room.
  • Installed piping at the Utility Tunnel.
  • Started forming and rebar installation at the Acid Scrubber Pad.
  • Completed emergency work to convert the East Holding Tank to a temporary sludge storage tank.
  • Began demo at the West Holding Tank roof due to the collapse and performed structural inspection of the walls.

August 2023

  • Procured additional masonry materials, additional structural and miscellaneous steel, additional valves, ductile iron piping, and other mechanical items, JMS conveyors, Velodyne polymer feed equipment, Evoqua gas membrane equipment, and World Water Works Sidestream equipment.
  • Worked on Sludge Phase 4 & 5 work including completing the piping and temporary wiring associated with relocating the existing sludge transfer pump.
  • Continued installing rebar and setting forms for the Upper Deck and completed the first slab pour.
  • Continued installing the brick veneer around the Biosolids Building.
  • Completed removing debris from the West Holding Tank from the roof that failed.
  • Installed vinyl ester coating for the FRP tank pads at the polymer area.
  • Installed sludge screening piping at the Polymer area.
  • Installed the FRP storage tanks.
  • Installed the THP Cooling Tower support steel.
  • Worked on installing the sludge cooling loop piping at the THP Pad.
  • Installed pipe supports at the Utility Corridor.
  • Worked on the Acid Scrubber Pad and under slab utilities.

July 2023

  • Procured the Odor Control Pad and Waste Gas Flare pad reinforcing steel, brick materials, structural and miscellaneous steel, electrical cable, additional valves, ductile iron piping, stainless steel piping and other mechanical items, HVAC duct accessories, R.E. Pedrotti instruments and Varec gas safety equipment.
  • Relocated the fire hydrant near the THP pad.
  • Worked on Sludge Phase 4 & 5 work including relocating the existing sludge transfer pump, installed temporary piping for the relocated pump and rerouted the supernatant lines.
  • Poured the invert in the new Sludge Wetwell.
  • Started installing hatches on the Upper Deck.
  • Continued installing rebar and setting forms for the Upper Deck.
  • Worked on some storm drain lines south of the Biosolids Building.
  • Started installing the brick veneer around the Biosolids Building.
  • Continued removing debris from the West Holding Tank from the roof that failed.

June 2023

  • Procured Sidestream reinforcing steel, Sulfuric Acid Chemical Feed System, FRP grating, structural and miscellaneous steel, additional valves, ductile iron piping and other mechanical items, R.E. Pedrotti instruments and Varec gas safety equipment.
  • Completed the balance of the Operating Floor concrete walls.
  • Completed installing the Upper Deck shoring and began installing rebar.
  • Completed the Sludge Wetwell water tightness testing.
  • Worked on several yard piping lines, including the sludge lines from the Biosolids Building to the THP, sludge lines from the Utility Corridor to the Sludge Wetwell, sludge feed line from the EQ tank to the Sidestream area and some storm drain lines south of the Biosolids Building.
  • Continued forming and pouring the pedestals at the Cake Loadout, placed the gravel fill and started forming and installing rebar at the operating level slab.
  • Started work on installing the West Holding Tank manways and demoing the roof.

May 2023

  • Procured additional ductile iron piping and other mechanical items, bar joists & metal decking materials, two FRP polymer storage tanks, Sidestream instrumentation and Mezzner panels, and two Huber In-Line Sludge Screens.
  • Continued forming and pouring the Operating Floor walls.
  • Continued installing the Upper Deck shoring.
  • Completed the Elevator Shaft masonry walls at the Operating Floor.
  • Worked on repairing the existing Elevator Shaft walls.
  • Continued work on the Pre-THP silo erection.
    Placed the concrete fill at Sidestream Reactor No.2.
  • Continued electrical rough-in at the Cambi equipment.
  • Worked on several yard piping lines, including the sludge lines from the Biosolids Building to the THP, sludge lines from the Utility Corridor to the Sludge Wetwell and the sludge feed line from the EQ tank to the Sidestream area.
  • Continued forming and pouring the pedestals at the Cake Loadout.

April  2023

  • Procured additional ductile iron piping and other mechanical items, masonry materials, four FRP polymer storage tanks, Sidestream mixing equipment and additional I&C instruments.
  • Continued forming and pouring the Operating Floor walls.
  • Began installing the Upper Deck shoring
  • Started installing masonry walls at the Operating Floor.
  • Installed the Pre-THP Centrifuge Feed pumps and Pre-THP Cake pumps
  • Continued working on the Pre-THP silo erection.
  • Continued electrical rough-in at the Cambi equipment.
  • Completed forming and pouring the East Holding Tank ring beams
  • Continued forming the short walls and columns at the Cake Loadout.

March 2023

  • Final design was completed.
  • Procured additional ductile iron piping and other mechanical items, procured some fabricated structural steel, Neenah cast iron grating and embeds, five progressive cavity pumps and the balance of the Upper Level reinforcing steel.
  • Formed and poured the balance of the Operating Floor columns for the Solids Building.
  • Continued forming and pouring the walls for the Solids Building.
  • Installed the two Sludge Coolers on the THP pad.
  • Continued working on the Pre-THP silo erection.
  • Completed erecting the THP canopy.
  • Continued electrical rough-in at the Cambi equipment.
  • Continued forming and pouring the East Holding Tank ring beams.
  • Worked on forming the short walls and columns at the Cake Loadout.

February 2023

  • Procured additional ductile iron piping and other mechanical items, procured the bridge crane hoist, two FRP polymer storage tanks and several I&C components.
  • Completed the masonry work associated with the relocated Elevator Control Room on the Admin Building. 
  • Formed and poured additional Operating Floor columns and walls.
  • Installed the Pre-THP Cake Silos structural support steel.
  • Began erecting the THP canopy structural support steel.
  • Continued electrical rough-in at the Cambi equipment.
  • Continued forming and pouring the East Holding Tank ring beams.
  • Worked on underslab drainage piping at the Cake Loadout area.
  • Removed the existing DAF 1 dome.

January 2023

  • Procured additional ductile iron piping and other mechanical items, procured the bridge crane, additional Pre-Engineered Metal Building component and Vaughan chopper pumps and mixing systems.
  • Formed and poured additional Operating Floor columns and walls.
  • Worked on install drain piping at the Biosolids Building basement and Operating Floor.
  • Continued electrical rough-in at the Cambi equipment and continued forming and rebar installation at the East Holding Tank ring beams.
  • Completed the underslab drainage piping from the Cake Loadout area.
  • Completed additional demo at the Holding Tank Room.
  • Worked on removing the existing equipment from DAF 1 & 2.

Click here to view construction work completed in 2021 and 2022.

    Blue River Biosolids Facility 2023 Year in Review

    Check out the construction progress at KC Water’s Blue River Wastewater Treatment Plant (WWTP)....

    Micro Aeration = Renewable Energy

    What does it all mean? Anaerobic means “without oxygen”. Micro aeration is adding a small amount...

    Blue River Biosolids Facility 2022 Year in Review

    It has been a productive year at KC Water’s Blue River Wastewater Treatment Plant (WWTP). Crews have been hard at work at the Blue River Biosolids Facility to keep this massive plant upgrade on time and on budget. Take a look at the progress made throughout 2022.